Hi

I saw in this link, revert is only supported in Design node:

reverting-a-bundle-on-the-design-node

How ever I did see this sentence here:

versioning

"Each bundle can then link to a specific version of a code environment, and versions of a given code environment are not removed, allowing for rolling back to a previous version of a project without risking to not be able to rebuild the exact same code environment"

what does it means? I didn't understand how roll back works in automation node. is there any example?

Tagged:

Best Answer

  • AgatheG
    AgatheG Dataiker, Registered Posts: 37 Dataiker
    Answer ✓

    Hi arielma,

    In the documentation you quote, "rolling back to a previous version of a project" alludes to the activation of a bundle in the automation node, aka "the process of extracting the metadata and additional data of a bundle to make it the current state of the project on the Automation node" (see https://doc.dataiku.com/dss/latest/bundles/importing.html#activating-a-bundle).

    Capture d’écran 2021-01-17 à 11.50.17.pngThis can be done by clicking on the Activate button here, and can be considered as the equivalent of reverting to a bundle on a Design node.

    Hope this helps,

    Agathe

Answers

  • arielma2304
    arielma2304 Registered Posts: 47 ✭✭✭✭

    Ok, so just to validate I understand.

    Assuming I have bundle version named "test" with scenario named "SMOKE_test" which is currently activate. In case the "SMOKE_test" scenario run failed, I can choose other bundle to activate so that actually like revert a bundle?

  • AgatheG
    AgatheG Dataiker, Registered Posts: 37 Dataiker

    Hi,

    Sorry for the delay! I am not sure to fully understand your comment. You can indeed revert to a previous bundle, however I do not get why you mentioned scenarios ?

    --